Dept. of Trans. PROGRESS Serial No. Contract No. 23-116-18-22 05-1K7004 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 97% Location: Federal Project: 05-MON-1-64.4/64.4 NONE Progress payment No. 021 Payment period ending: 04-20-23 AMERICAN CIVIL CONSTRUCTORS WEST COAST LLC 2990 BAY VISTA CT #D BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,037,014.25 20,277.00 2. a. Extra Work 87,198.53 0.00 b. Adustment Comp. -12,048.75 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,112,164.03 20,277.00 5. Mobilization 440,000.00 0.00 6. Total Work Completed 4,552,164.03 7. Deductions -18,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,534,164.03 20,277.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 20,277.00