Dept. of Trans. PROGRESS Serial No. Contract No. 22-115-17-02 05-1M3904 PROGRESS PAYMENT VOUCHER %complete: %time: 48% 23% Location: Federal Project: 05-MON-1-R80.3 NONE 05-SBT-156-2.7 05-SCR-1-R3.2/12.9 Progress payment No. 006 Payment period ending: 04-20-22 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 642,828.48 0.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 642,828.48 0.00 5. Mobilization 147,250.00 0.00 6. Total Work Completed 790,078.48 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 790,078.48 10,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,000.00