Dept. of Trans. PROGRESS Serial No. Contract No. 23-058-09-19 05-1M4604 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 86% Location: Federal Project: 05-MON-1-44.5/44.5 STER-39AC(4) Progress payment No. 008 Payment period ending: 02-20-23 FEC FUTURE CONTRACTORS AND ENGINEERS INC 184 TECHNOLOGY DRIVE #205 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,073,407.56 221,915.20 2. a. Extra Work 12,706.46 1,623.94 b. Adustment Comp. -1,365.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,084,749.02 223,539.14 5. Mobilization 140,400.00 0.00 6. Total Work Completed 1,225,149.02 7. Deductions -59,478.80 -55,478.80 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,165,670.22 168,060.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 168,060.34