Dept. of Trans. PROGRESS Serial No. Contract No. 23-083-14-59 05-1M4604 PROGRESS PAYMENT VOUCHER %complete: %time: 82% 87% Location: Federal Project: 05-MON-1-44.5/44.5 STER-39AC(4) Progress payment No. 009 Payment period ending: 03-20-23 FEC FUTURE CONTRACTORS AND ENGINEERS INC 184 TECHNOLOGY DRIVE #205 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,097,343.16 23,935.60 2. a. Extra Work 12,706.46 0.00 b. Adustment Comp. -1,365.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,108,684.62 23,935.60 5. Mobilization 140,400.00 0.00 6. Total Work Completed 1,249,084.62 7. Deductions -4,000.00 55,478.80 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,245,084.62 79,414.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 79,414.40