Dept. of Trans. SEMI-FINAL Serial No. Contract No. 22-257-19-45 05-1M6504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SCR-1-0.0 NONE 05-SCR-9 05-SCR-236 Progress payment No. 020 Payment period ending: 01-31-22 GRANITE CONSTRUCTION COMPANY 580 WEST BEACH ST WATSONVILLE CA 95076 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 10,157,583.77 42,543.88 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 10,157,583.77 42,543.88 5. Mobilization 6. Total Work Completed 10,157,583.77 7. Deductions -20,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,137,583.77 42,543.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 42,543.88