Dept. of Trans. PROGRESS Serial No. Contract No. 20-314-20-54 05-1M7004 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 47% Location: Federal Project: 05-MON-1-0.0 NONE Progress payment No. 001 Payment period ending: 11-05-20 PTM GENERAL ENGINEERING SERVICES INC PO BOX 7745 RIVERSIDE CA 92513 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 69,963.47 69,963.47 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 69,963.47 69,963.47 5. Mobilization 6. Total Work Completed 69,963.47 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 69,963.47 69,963.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 69,963.47