Dept. of Trans. SEMI-FINAL Serial No. Contract No. 24-033-11-16 05-1M7404 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-VAR-101-70.5/71.6 SSTG-000C(546) Progress payment No. 005 Payment period ending: 07-28-23 CAL STRIPE INC 2040 E STEEL RD COLTON CA 92324 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,379,192.60 0.00 2. a. Extra Work b. Adustment Comp. -6,310.86 -6,310.86 3. Materials on Hand 4. Earned Subject to Retention 1,372,881.74 -6,310.86 5. Mobilization 190,203.00 0.00 6. Total Work Completed 1,563,084.74 7. Deductions -50,395.50 -30,395.50 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,512,689.24 -36,706.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -36,706.36