Dept. of Trans. PROGRESS Serial No. Contract No. 24-093-08-10 05-1M7604 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 98% Location: Federal Project: 05-MON-101-81.0/81.5 CDSL-6205(31) Progress payment No. 004 Payment period ending: 03-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,542,973.94 7,920.00 2. a. Extra Work 62,738.31 62,738.31 b. Adustment Comp. -24,515.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,581,197.25 70,658.31 5. Mobilization 187,000.00 0.00 6. Total Work Completed 1,768,197.25 7. Deductions -50,000.00 -50,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,718,197.25 20,658.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 20,658.31