Dept. of Trans. FINAL Serial No. Contract No. 25-183-15-01 05-1M7604 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-MON-101-81.0/81.5 CDSL-6205(31) Progress payment No. 010 Payment period ending: 05-24-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,609,471.86 0.00 2. a. Extra Work 69,000.38 0.00 b. Adustment Comp. -13,279.14 -2,128.44 3. Materials on Hand 4. Earned Subject to Retention 1,665,193.10 -2,128.44 5. Mobilization 187,000.00 0.00 6. Total Work Completed 1,852,193.10 7. Deductions 0.00 74,780.13 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,852,193.10 72,651.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 72,651.69