Dept. of Trans. PROGRESS Serial No. Contract No. 20-328-14-58 05-1M7904 PROGRESS PAYMENT VOUCHER %complete: %time: 3% 15% Location: Federal Project: 05-SCR-236-2.1/15.5 NONE Progress payment No. 001 Payment period ending: 11-20-20 ARBORWORKS INC 40094 HWY 49 #A OAKHURST CA 93644 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 234,987.21 234,987.21 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 234,987.21 234,987.21 5. Mobilization 6. Total Work Completed 234,987.21 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 234,987.21 234,987.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 234,987.21