Dept. of Trans. SEMI-FINAL Serial No. Contract No. 22-062-17-21 05-1M8104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SCR-17-2.1/2.2 NONE Progress payment No. 002 Payment period ending: 01-21-22 A TEICHERT & SON INC 400 SUNRISE AVE #300 ROSEVILLE CA 95661 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 567,814.43 567,814.43 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 567,814.43 567,814.43 5. Mobilization 6. Total Work Completed 567,814.43 7. Deductions -30,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 537,814.43 567,814.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 567,814.43