Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 22-307-13-23 05-1N3004 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SB-1-R25.0 NONE 05-SB-154-R11.5 05-SB-166-R24.9/R69.9 Progress payment No. 006 Payment period ending: 10-04-22 VELARDE CONCRETE CONSTRUCTION INC 523 S. BRAND BLVD, #201 SAN FERNANDO CA 91340 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 574,443.14 14,613.33 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 574,443.14 14,613.33 5. Mobilization 120,002.00 0.00 6. Total Work Completed 694,445.14 7. Deductions -22,000.00 19,913.31 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 672,445.14 34,526.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 34,526.64