Dept. of Trans. PROGRESS Serial No. Contract No. 21-299-15-58 05-1N4104 PROGRESS PAYMENT VOUCHER %complete: %time: 71% 92% Location: Federal Project: 05-MON-1-27.2/27.6 NONE 05-MON-1-29.6/36.8 Progress payment No. 007 Payment period ending: 10-20-21 PAPICH CONSTRUCTION COMPANY INC 398 SUNRISE TERRACE ARROYO GRANDE CA 93420 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 17,504,989.43 1,842,066.97 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 17,504,989.43 1,842,066.97 5. Mobilization 6. Total Work Completed 17,504,989.43 7. Deductions -8,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,496,989.43 1,842,066.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,842,066.97