Dept. of Trans. SEMI-FINAL Serial No. Contract No. 23-024-10-22 05-1N6504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SLO-166-70.6/74.6 NONE Progress payment No. 005 Payment period ending: 09-16-22 GRIFFITH COMPANY 1128 CARRIER PKWY AV BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,059,458.40 -11,347.20 2. a. Extra Work b. Adustment Comp. 86,533.64 86,533.64 3. Materials on Hand 4. Earned Subject to Retention 1,145,992.04 75,186.44 5. Mobilization 6. Total Work Completed 1,145,992.04 7. Deductions -10,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,135,992.04 85,186.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 85,186.44