Dept. of Trans. PROGRESS Serial No. Contract No. 22-171-13-28 05-1P0404 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 46% Location: Federal Project: 05-SLO-46-9.7/9.7 NONE Progress payment No. 005 Payment period ending: 06-20-22 WHITAKER CONSTRUCTION GROUP INC 2752 CONCRETE CT PASO ROBLES CA 93446 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 650,533.15 126,512.63 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 650,533.15 126,512.63 5. Mobilization 6. Total Work Completed 650,533.15 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 650,533.15 126,512.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 126,512.63