Dept. of Trans. PROGRESS Serial No. Contract No. 22-115-17-32 05-1P3404 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 83% Location: Federal Project: 05-MON-156-2.5/2.5 NONE 05-SBT-25-44.7/44.7 05-MON-101-48.7/48.7 05-MON-198-7.1/7.1 Progress payment No. 003 Payment period ending: 04-20-22 PRECISION GRADE INC PO BOX 90 SAN JUAN BAUTISTA CA 95045 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 381,104.63 61,521.16 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 381,104.63 61,521.16 5. Mobilization 6. Total Work Completed 381,104.63 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 381,104.63 61,521.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 61,521.16