Dept. of Trans. PROGRESS Serial No. Contract No. 24-171-09-29 05-1P5304 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 38% Location: Federal Project: 05-SCR-129-L1.1/L1.5 NONE 05-SCR-152-T0.3/T2.5 Progress payment No. 009 Payment period ending: 06-13-24 BORTOLUSSI AND WATKIN INC 77 LARKSPUR ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 846,058.45 259,474.00 2. a. Extra Work 14,080.00 14,080.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 860,138.45 273,554.00 5. Mobilization 112,800.00 0.00 6. Total Work Completed 972,938.45 7. Deductions -15,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 957,938.45 273,554.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 273,554.00