Dept. of Trans. PROGRESS Serial No. Contract No. 24-295-11-25 05-1P5324 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 54% Location: Federal Project: 05-SBT-156-2.7/2.7 NONE Progress payment No. 016 Payment period ending: 10-20-24 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 696,633.35 820.80 2. a. Extra Work 19,800.00 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 716,433.35 820.80 5. Mobilization 52,555.00 0.00 6. Total Work Completed 768,988.35 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 768,988.35 820.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 820.80