Dept. of Trans. PROGRESS Serial No. Contract No. 24-204-13-44 05-1P5354 PROGRESS PAYMENT VOUCHER %complete: %time: 75% 9% Location: Federal Project: 05-SLO-1-12.1/12.2 NONE Progress payment No. 005 Payment period ending: 07-18-24 R BURKE CORP PO BOX 957 SAN LUIS OBISPO CA 93406-0957 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 994,389.59 319,562.09 2. a. Extra Work 12,172.23 12,172.23 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,006,561.82 331,734.32 5. Mobilization 85,000.00 4,250.00 6. Total Work Completed 1,091,561.82 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,081,561.82 325,984.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 325,984.32