Dept. of Trans. PROGRESS Serial No. Contract No. 24-143-13-04 05-1P5374 PROGRESS PAYMENT VOUCHER %complete: %time: 46% 20% Location: Federal Project: 05-SB-135-15.5/15.8 NONE Progress payment No. 004 Payment period ending: 05-20-24 R BURKE CORP PO BOX 957 SAN LUIS OBISPO CA 93406-0957 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 473,254.20 35,739.00 2. a. Extra Work 1,035.00 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 474,289.20 35,739.00 5. Mobilization 85,500.00 0.00 6. Total Work Completed 559,789.20 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 559,789.20 35,739.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 35,739.00