Dept. of Trans. PROGRESS Serial No. Contract No. 23-083-16-03 05-1P6304 PROGRESS PAYMENT VOUCHER %complete: %time: 72% 20% Location: Federal Project: 05-MON-68-3.5/3.5 NONE Progress payment No. 008 Payment period ending: 03-20-23 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 267,817.19 103,629.01 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 267,817.19 103,629.01 5. Mobilization 6. Total Work Completed 267,817.19 7. Deductions 0.00 12,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 267,817.19 115,629.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 115,629.01