Dept. of Trans. PROGRESS Serial No. Contract No. 22-361-12-16 05-1P8804 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 40% Location: Federal Project: 05-MON-1-0.1/2.7 NONE 05-SLO-1-71.4/71.4 Progress payment No. 001 Payment period ending: 12-20-22 S CHAVES CONSTRUCTION INC 11545 LOS OSOS VALLEY RD UNIT SAN LUIS OBISPO CA 93405 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 260,621.70 260,621.70 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 260,621.70 260,621.70 5. Mobilization 6. Total Work Completed 260,621.70 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 260,621.70 260,621.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 260,621.70