Dept. of Trans. PROGRESS Serial No. Contract No. 23-144-09-03 05-1Q0604 PROGRESS PAYMENT VOUCHER %complete: %time: 24% 22% Location: Federal Project: 05-SLO-1-12.6/12.7 NONE Progress payment No. 003 Payment period ending: 05-20-23 SOUZA CONSTRUCTION INC PO BOX 3810 SAN LUIS OBISPO CA 93403 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 165,101.43 29,720.34 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 165,101.43 29,720.34 5. Mobilization 6. Total Work Completed 165,101.43 7. Deductions -2,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 163,101.43 29,720.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 29,720.34