Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 23-033-15-52 05-1Q2304 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 20% Location: Federal Project: 05-MON-1-21.0/65.7 NONE Progress payment No. 001 Payment period ending: 01-20-23 S CHAVES CONSTRUCTION INC 11545 LOS OSOS VALLEY RD UNIT SAN LUIS OBISPO CA 93405 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 62,207.50 62,207.50 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 62,207.50 62,207.50 5. Mobilization 6. Total Work Completed 62,207.50 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 52,207.50 52,207.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 52,207.50