Dept. of Trans. PROGRESS Serial No. Contract No. 25-297-07-35 05-1Q4704 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 88% Location: Federal Project: 05-SLO-58-51.0/57.2 NONE Progress payment No. 004 Payment period ending: 10-20-25 GRIFFITH COMPANY 3050 E BIRCH ST BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,948,535.61 218,393.78 2. a. Extra Work b. Adustment Comp. -13,810.13 -13,810.13 3. Materials on Hand 4. Earned Subject to Retention 3,934,725.48 204,583.65 5. Mobilization 435,770.50 0.00 6. Total Work Completed 4,370,495.98 7. Deductions -15,437.51 -1,437.51 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,355,058.47 203,146.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 203,146.14