Dept. of Trans. PROGRESS Serial No. Contract No. 23-207-12-41 05-1Q7504 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 56% Location: Federal Project: 05-SB-101-5.3/10.5 NONE Progress payment No. 004 Payment period ending: 07-20-23 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 359,155.25 68,138.59 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 359,155.25 68,138.59 5. Mobilization 6. Total Work Completed 359,155.25 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 359,155.25 68,138.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 68,138.59