Dept. of Trans. PROGRESS Serial No. Contract No. 23-332-10-17 05-1Q7604 PROGRESS PAYMENT VOUCHER %complete: %time: 68% 100% Location: Federal Project: 05-MON-1-71.8/20.9 NONE Progress payment No. 009 Payment period ending: 11-20-23 S CHAVES CONSTRUCTION INC 11545 LOS OSOS VALLEY RD UNIT SAN LUIS OBISPO CA 93405 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 14,650,146.88 1,014,812.51 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 14,650,146.88 1,014,812.51 5. Mobilization 6. Total Work Completed 14,650,146.88 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,650,146.88 1,014,812.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,014,812.51