Dept. of Trans. PROGRESS Serial No. Contract No. 24-025-09-11 05-1Q8704 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 100% Location: Federal Project: 05-SB-1-1.7/0.0 NONE Progress payment No. 017 Payment period ending: 01-20-24 R BURKE CORP PO BOX 957 SAN LUIS OBISPO CA 93406-0957 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 2,946,068.54 8,462.66 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,946,068.54 8,462.66 5. Mobilization 6. Total Work Completed 2,946,068.54 7. Deductions -10,000.00 -8,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,936,068.54 462.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 462.66