Dept. of Trans. PROGRESS Serial No. Contract No. 23-284-15-39 05-1Q9604 PROGRESS PAYMENT VOUCHER %complete: %time: 31% 20% Location: Federal Project: 05-MON-1-100.0/1.0 NONE Progress payment No. 002 Payment period ending: 10-05-23 A TEICHERT & SON INC 3500 AMERICAN RIVER DRIVE SACRAMENTO CA 95864 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 574,971.96 248,469.78 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 574,971.96 248,469.78 5. Mobilization 6. Total Work Completed 574,971.96 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 574,971.96 248,469.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 248,469.78