Dept. of Trans. PROGRESS Serial No. Contract No. 23-207-14-03 05-1R1504 PROGRESS PAYMENT VOUCHER %complete: %time: 7% 18% Location: Federal Project: 05-MON-198-20.8/20.8 NONE Progress payment No. 001 Payment period ending: 07-20-23 BROUGH CONSTRUCTION INC. 634 PRINTZ RD ARROYO GRANDE CA 93420 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 216,964.35 216,964.35 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 216,964.35 216,964.35 5. Mobilization 6. Total Work Completed 216,964.35 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 216,964.35 216,964.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 216,964.35