Dept. of Trans. PROGRESS Serial No. Contract No. 24-323-19-02 05-1R1904 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 60% Location: Federal Project: 05-MON-1-7.2/9.2 NONE Progress payment No. 008 Payment period ending: 11-20-24 JOHN MADONNA CONSTRUCTION CO INC PO BOX 5310 SAN LUIS OBISPO CA 93403 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 47,216,712.21 2,480,516.64 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 47,216,712.21 2,480,516.64 5. Mobilization 6. Total Work Completed 47,216,712.21 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 47,216,712.21 2,480,516.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,480,516.64