Dept. of Trans. PROGRESS Serial No. Contract No. 25-142-11-27 05-1R1904 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 92% Location: Federal Project: 05-MON-1-7.2/9.2 NONE Progress payment No. 014 Payment period ending: 05-20-25 JOHN MADONNA CONSTRUCTION CO INC PO BOX 5310 SAN LUIS OBISPO CA 93403 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 71,602,877.15 5,353,667.07 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 71,602,877.15 5,353,667.07 5. Mobilization 6. Total Work Completed 71,602,877.15 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 71,602,877.15 5,353,667.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,353,667.07