Dept. of Trans. PROGRESS Serial No. Contract No. 24-205-12-34 05-1R6604 PROGRESS PAYMENT VOUCHER %complete: %time: 44% 43% Location: Federal Project: 05-0SB-246-10.9/19.3 NONE 05-0SB-246-10.9/10.9 Progress payment No. 001 Payment period ending: 07-20-24 R BURKE CORP PO BOX 957 SAN LUIS OBISPO CA 93406-0957 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 233,826.80 233,826.80 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 233,826.80 233,826.80 5. Mobilization 6. Total Work Completed 233,826.80 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 233,826.80 233,826.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 233,826.80