Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 25-323-07-23 05-1R7304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SB-135-R7.2/M9.7 NONE Progress payment No. 004 Payment period ending: 10-28-25 CALPORTLAND CONSTRUCTION PO BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,268,267.89 52,875.00 2. a. Extra Work b. Adustment Comp. -29,238.77 -29,238.77 3. Materials on Hand 4. Earned Subject to Retention 2,239,029.12 23,636.23 5. Mobilization 270,000.00 0.00 6. Total Work Completed 2,509,029.12 7. Deductions -99,750.00 -60,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,409,279.12 -36,363.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -36,363.77