Dept. of Trans. PROGRESS Serial No. Contract No. 25-356-13-14 05-1R7504 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 100% Location: Federal Project: 05-SB-101-R0.0/2.2 NONE Progress payment No. 005 Payment period ending: 12-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,687,265.46 49,069.00 2. a. Extra Work 125,825.26 68,942.61 b. Adustment Comp. -12,819.52 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,800,271.20 118,011.61 5. Mobilization 309,000.00 0.00 6. Total Work Completed 3,109,271.20 7. Deductions -40,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,069,271.20 128,011.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 128,011.61