Dept. of Trans. PROGRESS Serial No. Contract No. 24-262-14-15 05-1S0904 PROGRESS PAYMENT VOUCHER %complete: %time: 71% 60% Location: Federal Project: 05-SCR-1-304.0/30.4 NONE 05-SCR-1-304.0/30.4 Progress payment No. 003 Payment period ending: 09-13-24 SERAFIX ENGINEERING CONTRACTORS INC 7 CROW CANYON CT #250 SAN RAMON CA 94583 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 315,048.13 23,123.14 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 315,048.13 23,123.14 5. Mobilization 6. Total Work Completed 315,048.13 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 315,048.13 23,123.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 23,123.14