Dept. of Trans. PROGRESS Serial No. Contract No. 25-233-10-39 05-1S3604 PROGRESS PAYMENT VOUCHER %complete: %time: 14% 30% Location: Federal Project: 05-SCR-9-12.1/12.1 NONE Progress payment No. 011 Payment period ending: 08-20-25 GRANITE CONSTRUCTION COMPANY 580 WEST BEACH ST WATSONVILLE CA 95076 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 647,108.39 2,154.41 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 647,108.39 2,154.41 5. Mobilization 6. Total Work Completed 647,108.39 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 647,108.39 12,154.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 12,154.41