Dept. of Trans. PROGRESS Serial No. Contract No. 26-264-07-51 05-1S5604 PROGRESS PAYMENT VOUCHER %complete: %time: 31% 55% Location: Federal Project: 05-0SB-101-142.0/14.2 NONE 05-0SB-101-142.0/14.2 Progress payment No. 002 Payment period ending: 09-20-26 BROUGH CONSTRUCTION INC. 530 PAULDING CIR #B ARROYO GRANDE CA 93420 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 147,427.93 29,338.40 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 147,427.93 29,338.40 5. Mobilization 6. Total Work Completed 147,427.93 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 147,427.93 29,338.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 29,338.40