Dept. of Trans. FINAL Serial No. Contract No. 26-279-15-12 05-1T4104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SLO-41-495.0/49.5 NONE 05-SLO-41-495.0/49.5 Progress payment No. 004 Payment period ending: 03-24-26 DRILL TECH DRILLING & SHORING INC 2200 WYMORE WAY ANTIOCH CA 94509 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 952,852.58 46,051.37 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 952,852.58 46,051.37 5. Mobilization 6. Total Work Completed 952,852.58 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 952,852.58 56,051.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 56,051.37