Dept. of Trans. PROGRESS Serial No. Contract No. 05-238-08-10 08-0F4704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 73% 08-RIV-111-53.0/56.2 Federal Project: NONE Progress payment No. 03 Payment period ending: 08-19-05 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 756,997.77 16,284.40 2.a. Extra Work 18,086.35 18,086.35 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 775,084.12 34,370.75 5. Mobilization 6. Total Work Completed 775,084.12 7. Deductions 8. a.Contract Retentions -38,754.21 -1,718.54 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 736,329.91 32,652.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 32,652.21 Dept. of Trans. PROGRESS Serial No. Contract No. 05-235-08-53 05-282804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 57% 65% 05-SB-150-1.0/R1.7 Federal Project: 05-VEN-150-D1.1/D1.5 ACST-P150(21) P-P150(21) ACBR-P150(E) Progress payment No. 04 Payment period ending: 08-20-05 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,100,581.66 482,881.25 2.a. Extra Work 114,273.00 82,247.35 b. Adjustment Comp. 8,745.00 0.00 3. Materials on Hand 38,588.89 38,588.89 4. Earned Subject to Retention 2,262,188.55 603,717.49 5. Mobilization 275,000.00 13,750.00 6. Total Work Completed 2,498,599.66 7. Deductions -27,475.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,509,713.55 617,467.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 617,467.49