Dept. of Trans. PROGRESS Serial No. Contract No. 03-140-14-15 05-314204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 14% 5% 05-SLO-101-28.4/28.7 Federal Project: ACNH-Q101(26) Progress payment No. 03 Payment period ending: 05-20-03 R BURKE CORPORATION P O BOX 957 SAN LUIS OBISPO CA 934060957 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 75,150.00 10,900.00 2.a. Extra Work b. Adjustment Comp. 18,333.00 18,333.00 3. Materials on Hand 4. Earned Subject to Retention 93,483.00 29,233.00 5. Mobilization 55,000.00 0.00 6. Total Work Completed 148,483.00 7. Deductions -2,408.62 0.00 8. a.Contract Retentions -9,348.30 -2,923.30 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 136,726.08 26,309.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 26,309.70