Dept. of Trans. PROGRESS Serial No. Contract No. 14-056-08-08 05-315804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 54% 31% 05-MON-101-100.0/101.3 Federal Project: 05-SBT-101-0.0/1.6 NH-P101 Progress payment No. 15 Payment period ending: 02-20-14 GCC/MCM, A JV P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,160,894.96 688,732.18 2.a. Extra Work 392,047.06 3,257.88 b. Adjustment Comp. 3. Materials on Hand 442,672.42 -23,302.50 4. Earned Subject to Retention 19,995,614.44 668,687.56 5. Mobilization 3,232,504.20 0.00 6. Total Work Completed 22,785,446.22 7. Deductions -40,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 23,188,118.64 668,687.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 668,687.56