Dept. of Trans. PROGRESS Serial No. Contract No. 14-203-13-11 05-315804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 43% 05-MON-101-100.0/101.3 Federal Project: 05-SBT-101-0.0/1.6 NH-P101 Progress payment No. 20 Payment period ending: 07-20-14 GCC/MCM, A JV P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,428,673.93 -724,008.76 2.a. Extra Work 2,009,103.72 1,574,057.07 b. Adjustment Comp. 229,311.29 229,311.29 3. Materials on Hand 410,513.88 0.00 4. Earned Subject to Retention 24,077,602.82 1,079,359.60 5. Mobilization 3,402,636.00 0.00 6. Total Work Completed 27,069,724.94 7. Deductions -80,000.00 19,432.71 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 27,400,238.82 1,098,792.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,098,792.31