Dept. of Trans. PROGRESS Serial No. Contract No. 15-112-14-11 05-315804 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 67% Location: Federal Project: 05-MON-101-100.0/101.3 NH-P101 05-SBT-101-0.0/1.6 Progress payment No. 029 Payment period ending: 04-20-15 GCC/MCM, A JV P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 31,912,337.98 1,360,864.08 2. a. Extra Work 2,209,134.97 29,804.47 b. Adustment Comp. 388,924.71 53,449.20 3. Materials on Hand 64,800.88 0.00 4. Earned Subject to Retention 34,575,198.54 1,444,117.75 5. Mobilization 3,402,636.00 0.00 6. Total Work Completed 37,913,033.66 7. Deductions -40,000.00 30,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 37,937,834.54 1,474,117.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,474,117.75