Dept. of Trans. PROGRESS Serial No. Contract No. 11-080-13-44 05-315924 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 33% 33% 05-MON-1-99.9/R101.5 Federal Project: NONE Progress payment No. 15 Payment period ending: 03-20-11 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,990,547.43 193,746.75 2.a. Extra Work 55,866.15 34,640.41 b. Adjustment Comp. -6,850.20 -6,850.20 3. Materials on Hand 115,105.00 -57,980.00 4. Earned Subject to Retention 3,154,668.38 163,556.96 5. Mobilization 950,000.00 0.00 6. Total Work Completed 3,989,563.38 7. Deductions -46,101.79 -37,391.58 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,058,566.59 126,165.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 126,165.38