Dept. of Trans. PROGRESS Serial No. Contract No. 11-206-10-09 05-315924 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 34% 45% 05-MON-1-99.9/R101.5 Federal Project: NONE Progress payment No. 19 Payment period ending: 07-20-11 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,052,290.43 16,968.00 2.a. Extra Work 187,371.39 0.00 b. Adjustment Comp. -6,850.20 0.00 3. Materials on Hand 144,023.96 28,918.96 4. Earned Subject to Retention 3,376,835.58 45,886.96 5. Mobilization 950,000.00 0.00 6. Total Work Completed 4,182,811.62 7. Deductions -10,447.24 -10,447.24 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,316,388.34 35,439.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 35,439.72