Dept. of Trans. PROGRESS Serial No. Contract No. 11-325-11-12 05-315924 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 47% 59% 05-MON-1-99.9/R101.5 Federal Project: NONE Progress payment No. 23 Payment period ending: 11-20-11 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,761,990.19 679,684.25 2.a. Extra Work 205,264.96 0.00 b. Adjustment Comp. -6,850.20 0.00 3. Materials on Hand 53,918.96 0.00 4. Earned Subject to Retention 5,014,323.91 679,684.25 5. Mobilization 950,000.00 0.00 6. Total Work Completed 5,910,404.95 7. Deductions -6,500.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,957,823.91 674,684.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 674,684.25