Dept. of Trans. PROGRESS Serial No. Contract No. 12-053-13-28 05-315924 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 53% 70% 05-MON-1-99.9/R101.5 Federal Project: NONE Progress payment No. 26 Payment period ending: 02-20-12 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,465,134.04 317,016.00 2.a. Extra Work 223,411.78 2,982.63 b. Adjustment Comp. -1,932.79 4,917.41 3. Materials on Hand 52,718.96 6,300.00 4. Earned Subject to Retention 5,739,331.99 331,216.04 5. Mobilization 950,000.00 0.00 6. Total Work Completed 6,636,613.03 7. Deductions -11,500.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,677,831.99 331,216.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 331,216.04