Dept. of Trans. PROGRESS Serial No. Contract No. 12-115-09-39 05-315924 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 55% 76% 05-MON-1-99.9/R101.5 Federal Project: NONE Progress payment No. 28 Payment period ending: 04-20-12 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,640,484.04 57,871.00 2.a. Extra Work 343,759.76 59,996.89 b. Adjustment Comp. 863.64 2,796.43 3. Materials on Hand 35,218.96 0.00 4. Earned Subject to Retention 6,020,326.40 120,664.32 5. Mobilization 1,000,000.00 0.00 6. Total Work Completed 6,985,107.44 7. Deductions -13,500.00 -2,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,006,826.40 118,664.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 118,664.32