Dept. of Trans. PROGRESS Serial No. Contract No. 12-262-11-08 05-315924 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 85% 71% 05-MON-1-99.9/R101.5 Federal Project: NONE Progress payment No. 33 Payment period ending: 09-20-12 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,882,742.80 729,503.94 2.a. Extra Work 612,076.13 968.44 b. Adjustment Comp. 224,696.50 0.00 3. Materials on Hand 16,516.22 -11,743.26 4. Earned Subject to Retention 10,736,031.65 718,729.12 5. Mobilization 1,000,000.00 0.00 6. Total Work Completed 11,719,515.43 7. Deductions -5,000.00 7,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,731,031.65 725,729.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 725,729.12